Move into new courthouse to begin in October
The move into Union County's new courthouse in Jonesboro is expected to begin in October.
The latest update on construction of the new courthouse was shared at last Friday morning's regular meeting of the Union County Board of Commissioners.
The meeting was at the community center in Jonesboro.
County courthouse construction project manager Mike Smith shared an update with the commissioners on work which had been done between May 4 and May 18.
Smith also presented a projected timeline for the project.
The time calls for:
•Setting of a cupola at the new courthouse on June 29.
•The lower level drywall to be hung and taped in June.
•Level 1 drywall to be hung and taped in July.
•The Union County sheriff's and 911 offices to move into the lower level of the new facility in October.
•Demolition of the old sheriff's office and four neighboring houses to follow the move.
•Offices in the old courthouse to begin moving into the new facility in December.
•Demolition of the old courthouse to begin in mid-January of 2013.
The Union County sheriff's and 911 offices are located in a building which is adjacent to the existing courthouse. The building formerly housed the county jail.
The courthouse project manager's report also highlighted other progress.
Charles Masonry is completing work in the lower level. Bricks were being laid at the south, east and west elevations, with cast stone placed on the sills, headers and capstones in assorted areas. Level 2 detention cells and the courtrooms were 85 percent complete.
Heartland Fire Protection was installing a sprinkler system in Levels 1 and 2. The lower level was complete.
Boilers, a water heater, air handlers, a water pressurer pump and plumbing were being installed at all levels.
Roof and overflow cast iron drains have been completely piped through the building from the roof to the basement level to connect to an exterior storm drain on Mississippi Street.
Steel studs and exterior sheathing with water/vapor proofing were applied at Level 1 and Level 2 exteriors, with work 95 percent complete by Miller Drywall.
Interior steels studs had been set to 100 percent at the lower level, 95 percent of Level 1 rooms and 50 percent of Level 2 rooms.
Lower level sheetrock application was begun Tuesday, May 15. Two truckloads of fire rated sheetrock and elevator shaft liner were stored in the building.
The exterior of the tower was being sheathed and
waterproofed. The cupola will be studded up with steel studs to accept metal panels which are on site.
Grover Mays Construction completed assembly of the tower stair treads and landings. Hand and safety rails were to be placed this week. Welding of numerous types of braces continues on the structure.
Tradesmen were installing heating, cooling and ventilating and exhaust ducts, as well as electrical and plumbing, at all levels. Rooftop cooling units were to have been set this week.
Roofers completed the upper roof. This week, a small lower roof was to have been installed.
Burkey Excavation will be contouring the site elevation on the north side of the building this week.
Water services for the new courthouse at Mississippi Street have been tapped into the main.
There was to have been a 3-inch domestic water supply and a 4-inch fire protection supply piped to the building soon, as well as a gas service line.