Courthouse project passes 200-day mark

The latest update on construction of Union County's new courthouse in Jonesboro was shared Friday, Aug. 3.

The report was presented at the Aug. 3 regular meeting of the Union County Board of Commissioners. The meeting was at the community center in Jonesboro.

Courthouse construction project manager Mike Smith prepared the report, which covered the period from July 20 through Friday, Aug. 3. Highlights follow:

Aug. 3 was the 218th day of construction at the new courthouse.

An 80-foot radio tower was assembled on-site, hoisted into position and secured. A concrete pad and wiring will be addressed during August.

A 200KW emergency generator weighing 11,000 pounds was scheduled to arrive Aug. 3.

A semi load of elevator parts arrived July 26. Installation of three elevators was started July 30 and is expected to take about 40 work days to complete.

Glass for the secure 911 and dispatch room has arrived. The glass is one-way and bullet-proof to withstand the following without failure: 10 rounds 9MM, the same impact point, fired from 20 feet.

The KSU room is being fitted for cable racks and electronic equipent stands plus thousands of feet of wiring.

The KSU room is the heartbeat of all the communications for the new courthouse.

The room for all three providers of telephone/cable/Internet/IT has been lined with fire resistant plywood to allow for the attachment of multiple wiring assemblies.

Installation of heating, cooling, ventilating and exhaust ducts, electrical and plumbing at all levels continues.

The lower level was more than 95 percent complete, with the exception of the mechanical room. Level 1 was 90 percent complete. Level 2 was 75 percent complete.

The tower roof was complete and the cupola cap is scheduled for delivery in August.

Aluminum window frames and insulated glass have been delivered and installation was planned on the north elevations.

A fire pump and two, 8,000-gallon fire protection tanks are slated for delivery during the week of Aug. 13.

Projected timelines follow:

The north parking area will begin to be shaped, curbed and paved over the next several weeks, weather permitting.

Four wood-framed houses on the east side of the courthouse grounds are slated to be demolished in stages starting in October and continuing through December.

The sheriff and 911 will move into the lower level on Oct. 1. Demolition of the old sheriff's office will follow the move.

Old courthouse offices will begin moving Jan. 1, 2013.

Demolition of the old courthouse will start in February 2013.


        Archive Section: 

        The Gazette-Democrat

        112 Lafayette St.
        Anna, Illinois 62906
        Office Number: (618) 833-2158
        Email: news@annanews.com

        Sign Up For Breaking News

        Stay informed on our latest news!