Courthouse soil test work done, design work continues
Several updates on the construction of a new courthouse in Union County were reported this week.
County officials say they are hoping that construction of the new facility will start in April 2011.
The information was shared at a regular meeting of the Union County Board of Commissioners.
The meeting was Monday afternoon at the county courthouse in Jonesboro.
Courthouse project manager Mike Smith reported that representatives of the HOK architectural firm in St. Louis met with county officials last week as part of the ongoing process to design the new courthouse.
Smith said that details are being refined for the new facility. A set of plans should be available soon which would show how the exterior and interior of the new courthouse could look.
Smith reported that soil tests were conducted last week on the courthouse grounds. No major problems are anticipated.
County officials also discussed costs related to removing debris when demolition of the existing structure is done. Demolition work is expected to begin in February.
The county also is in the process of purchasing structures adjacent to the existing courthouse as part of the construction project.
A building next to the existing offices of the sheriff and 911 program already has been purchased. That structure will serve as an office for the project manager and as a meeting site for the county board while the new courthouse is being built.
The county is looking into purchasing three other structures near the existing courthouse. The structures could be used as temporary office space during construction of the new building.
In other business at Monday's meeting:
Other Business
The county commis-sioners approved a tentative Fiscal Year budget for 2010-2011. The new fiscal year begins Dec. 1.
Completion of the tentative budget came at a daylong session the commissioners held on Monday. The commissioners have met six times in recent weeks to work on the budget.
Final approval of the new budget is expected at a special meeting set for 4 p.m. Tuesday, Nov. 30, at the courthouse.
Also on Monday, a vote was taken to make commissioners no longer eligible for health insurance provided by the county.