Courthouse project passes 225 days
Aug. 17 was the 228th day of construction at the new Union County Courthouse in Jonesboro.
An update on the project was shared at the most recent meeting of the Union County Board of Commissioners.
The meeting was Friday morning, Aug. 17, at the community center in Jonesboro.
The update on work through Aug. 17 was presented by courthouse construction project manager Mike Smith. Highlights from the report follow:
The west parking lot was closed to allow for demolition, excavation, installation of curbing and paving in conjunction with plans for the new courthouse.
An 80-foot radio tower has been assembled on-site, hoisted into position and secured. A concrete pad and wiring will be addressed as August comes to an end.
A 200KW emergency generator which weighed 11,000 pounds arrived Aug. 15. The generator was set on a seismic engineered concrete pad located at the southeast corner of the new building. Wiring into the building to switching devices was expected to follow.
Elevator workmen had installed about 75 percent of two of the three elevators. The third and largest public elevator will be started in September.
Two semi loads of cast stone arrived Aug. 1-2. Both loads were placed atop the building. One load is remaining to complete the capstone in September. Charles Masonry workmen cleared equipment off-site Aug. 17.
The secure ceiling for the detention area halls and workrooms had been installed. The ceiling is made of steel substructure covered with two layers of impact resistant drywall.
All of detention's one-way and bullet-proof glass has been installed.
The cupola's exterior metal wall system has been completed and was ready for glaziers to install window frames and glass panes. Delivery of the cupola cap is rescheduled in early October.
The north parking area has begun to be shaped, and will be curbed and paved over the next several weeks, weather permitting.
Two wood-framed houses on the east side of the grounds are slated to be demolished.
The current timeline for the project still calls for the Union County Sheriff's Office and 911 to move into the lower level of the new building on Oct. 1.
Remaining courthouse offices are slated to begin moving into the new facility on Jan. 1, 2013.
Demolition of the old courthouse and the sheriff's office is scheduled to begin in February 2013.